2025 City Street and Utility Project Newsletter (Aug. 29)
Published on Aug 29, 2025 10:22
PROPOSED TWO-WEEK CONSTRUCTION
SCHEDULE
Idaho Ave. N.
Sept. 2 – 6
- Curb and gutter installation on Tuesday.
- Concrete Driveway installation on Wednesday.
- Notices have been sent to each house affected by the concrete. Cars
should not drive across new curb or driveway for 7 days.
Sept. 8 – 12
- Grading of the roadway for first lift of asphalt.
- Backfilling of curb and topsoil for yards and seeding.
Jersey Ave. N.
Sept. 2 – 6
·
Watermain installation will continue, including services.
·
Sanitary sewer will begin on Monday September 2nd
and continue through the week.
Sept. 8 – 12
·
Finish up sewer installation and services.
·
Roadwork will begin including excavating existing soils and
installing sand and gravel.
Traffic Impacts and
Parking
During the construction period, there
will be no on-street parking on the following streets between 7 a.m.
to 7 a.m.
·
Idaho Ave. N. between 30th
Ave. N. and 31st Ave. on Tuesday and Wednesday next week. After Wednesday residents
can park on the street.
·
Jersey Ave. N. between 30th
Ave. North and Medicine Lake Road.
Weather Considerations
The project is weather-dependent,
and activities may be delayed if adverse conditions arise. We will keep residents
informed of any schedule changes as they occur.
Contact Information
For questions or concerns about the
construction project, do not hesitate to contact:
We appreciate your patience and
cooperation as we work to improve the streets and utilities in your
neighborhood. We will continue to keep you updated on the progress of the
project.
|