2025 City Street and Utility Project Newsletter (Aug. 29)
Published on Aug 29, 2025 10:22

Header Image for the street and utility reconstruction project newsletter

PROPOSED TWO-WEEK CONSTRUCTION SCHEDULE

Idaho Ave. N.

Sept. 2 – 6

  • Curb and gutter installation on Tuesday.
  • Concrete Driveway installation on Wednesday.
  • Notices have been sent to each house affected by the concrete. Cars should not drive across new curb or driveway for 7 days.

Sept. 8 – 12

  • Grading of the roadway for first lift of asphalt.
  • Backfilling of curb and topsoil for yards and seeding.

Jersey Ave. N.

Sept. 2 – 6

·       Watermain installation will continue, including services.

·       Sanitary sewer will begin on Monday September 2nd and continue through the week.

Sept. 8 – 12

·       Finish up sewer installation and services.

·       Roadwork will begin including excavating existing soils and installing sand and gravel.

Traffic Impacts and Parking

During the construction period, there will be no on-street parking on the following streets between 7 a.m. to 7 a.m.

·       Idaho Ave. N. between 30th Ave. N. and 31st Ave. on Tuesday and Wednesday next week. After Wednesday residents can park on the street.

·       Jersey Ave. N. between 30th Ave. North and Medicine Lake Road.

Weather Considerations
The project is weather-dependent, and activities may be delayed if adverse conditions arise. We will keep residents informed of any schedule changes as they occur.

Contact Information
For questions or concerns about the construction project, do not hesitate to contact:

We appreciate your patience and cooperation as we work to improve the streets and utilities in your neighborhood. We will continue to keep you updated on the progress of the project.