2026 City Street and Utility Project Newsletter - May 29
Published on May 29, 2026 09:31

This past week, the contractor finished all of the storm sewer work
and began lining the watermain. The watermain lining should be
substantially complete by the end of the week with final testing rolling into
next week.
Once lining is completed, water service line replacement will begin.
This work includes replacement of the water service from the main to the shut
off valve in your yard. The crew will work with residents to make sure they can
access their driveways or give them advanced notice to allow them to move their
vehicles prior to digging. This work is anticipated to take a couple weeks and
is planned to be done around mid June.
If you have any questions, please feel free to reach out to the
construction observer, Lucas Gross, at (612) 791-8423 or [email protected].
Thank
you for your patience as the city works to improve the infrastructure in your
neighborhood.
|