2026 City Street and Utility Project Newsletter - Aug. 21
Published on Aug 24, 2026 09:38

Streets and Utilities Reconstruction Newsletter
This past week, the contractor completed the reinstallation of mailboxes and restored all disturbed areas with sod or seed. The contractor will be responsible for watering it for 45 days or until Sunday, Oct. 4. If the sod is green and healthy on the 45th day of the warranty period, it will then be the homeowner's full responsibility to wa-ter and care for it. If the sod dies within the 45-day warranty period, the contractor will be responsible for replacing it.
The final layer of pavement is currently scheduled for mid-September.
If you have any questions, please contact Lucas Gross at 612-791-8423 or via email at [email protected].
Thank you for your patience as the city works to improve the infrastructure in your neighborhood.

Learn more at https://www.crystalmn.gov/our_city/public_works_projects.